Question

A spot welding operation performed on two pieces of steel yielded a nugget with a diameter of 5 mm and a thickness of 1 mm. The welding time was 0.1 s. The melting energy for the steel is 20 J/mm³ . Assuming the heat conversion efficiency as 10%, the power required for performing the spot welding operation is __________________ kW (round off to two decimal places)

Show Answer
Report

Answer :

Correct answer is : 26.179