Question Details

A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is

Options

A

3

B

9

C

27

D

81

Correct Answer :

9

Solution :

The correct option is 9.

To find the standard deviation of the critical path in a PERT (Program Evaluation and Review Technique) network, we use the statistical properties of independent activities along that path.

First, we relate the variance of the critical path to the variances of the individual activities. For a series of independent activities on the critical path, the total variance of the critical path (σp2) is the sum of the variances of each individual activity (σi2) on that path:
σp2=i=1nσi2

Here, we are given:
- The number of activities on the critical path, n=9
- The standard deviation of each individual activity, σi=3 for all i

First, we calculate the variance of a single activity:
σi2=32=9

Next, we sum the variances of all 9 activities to find the total variance of the critical path:
σp2=9×9=81

Finally, the standard deviation of the critical path (σp) is the square root of its total variance:
σp=σp2=81=9

Therefore, the standard deviation of the critical path is 9.